During vessel operations in Chile the vessel developed damage to the crane winch; drive shaft, brake and internal gearbox. The customer requested that the winch from crane #2 be relocated to crane #4.

In consultation with the procedure for winch removal was agreed. The hoisting winches were rotated through 90° and removed. The hoisting winch was removed by crane #3 and placed on the portside deck. The winch drum and gearbox was removed from the winch drum, and the winch boxed for transportation to shore workshop.

The winch from crane #2 was removed and installed into crane #4. Hydraulic and electrical set up was carried out to the relocated winch, and function tests were carried out to the crane.

Crane Winch Removal
Written by: PT.CALTAV INDONESIA
Reting: 4.6


PT.CALTAV INDONESIA is a company specialized in Hydraulic, Mechanical and Electrical system, HVAC, Servicing, overhaul and Commissioning for ship deck machineries and Ship deck crane, including Trading and other supplies for marine and offshore industries.


Follow me on Google+ | Twitter | Facebook | Linkedin | YouTube

Advertisement

No comments.

Leave a Reply